Keystone XL developer plans to start construction in 2019

Published:Tuesday | September 25, 2018 | 12:00 AM

The developer of the Keystone XL oil pipeline plans to start construction next year, after a US State Department review, ordered by a federal judge, concluded that major environmental damage from a leak is unlikely and could quickly be mitigated, a company spokesman said Monday.

TransCanada spokesman Matthew John said the company remains committed to moving ahead with the project following years of reviews from federal and state regulators. The company has already started preparing pipe yards, transporting pipe and mowing parts of the project's right-of-way in Montana and South Dakota, but TransCanada said in court documents it doesn't plan start construction in Nebraska in the first half of 2019.

The report, issued Friday from the Trump administration's State Department, drew criticism from environmental groups, who say they'll continue to fight the project they view as an environmental threat.

"The Trump administration sees no problem with building the Keystone XL - in other news, the grass is still green and the sky is still blue," said Kelly Martin, a campaign director for the Sierra Club.

 

Updated report

 

The updated, 338-page report was released a little more than a month after a federal judge in Montana ordered the US State Department to conduct a more thorough review of the pipeline's proposed pathway after Nebraska state regulators changed the route.

The original environmental impact study was issued in 2014, before Nebraska regulators approved a longer "mainline alternative" route that veered away from the company's preferred pathway. President Donald Trump approved a federal permit for the project in March 2017, reversing former President Barack Obama's decision to reject it amid concerns over greenhouse admissions.

The report said the US$8-billion, 1,184-mile pipeline would have a "negligible to moderate" environmental impact under its normal operations, and continuous monitoring and automatic shut-off valves would help company officials quickly identify a leak or rupture. Additionally, the report said TransCanada has a response plan in place that should mitigate the effects if it's implemented quickly.

"Prompt clean-up response would likely be capable of remediating the contaminated soil before the hazardous release reaches groundwater depth," the report said.

The latest State Department report is a draft that must still face public review and comments, but federal officials say they expect to have the final draft ready by December. In court documents from the Montana lawsuit, TransCanada's attorneys said they believe all the pending lawsuits will be resolved before construction begins.

The pipeline would carry up to 830,000 barrels of crude oil per day from Canada through Montana and South Dakota to Steele City, Nebraska, where it would connect with the original Keystone pipeline that runs down to Texas Gulf Coast refineries.